PMP Practice Test
Practise for the PMP with 810 exam-style questions, an explanation for every answer and stats that show what to study next.
What is the PMP exam?
The PMP exam is the Project Management Institute's test for its Project Management Professional certification: 180 questions in 240 minutes, across three domains. You must apply first, with 24 to 60 months of experience leading projects and 35 hours of training. PMI's handbook gives no numeric passing score.
PMP format change: what is different since July 2026
The outline changed in July 2026, and some pages still show the old numbers. Check any study material against this table.
| Detail | What older pages show | July 2026 outline |
|---|---|---|
| Time | 230 minutes | 240 minutes |
| Scored questions | 175 | 170, plus 10 pretest |
| People, Process, Business Environment | 42%, 50%, 8% | 33%, 41%, 26% |
| Tasks | 35 | 26 |
What are the PMP certification requirements?
You need 35 hours of training and a set amount of experience leading projects. The amount depends on your education:
| Education | Months leading projects |
|---|---|
| Secondary school | 60 |
| Associate-level or similar | 48 |
| Bachelor's or higher | 36 |
| Bachelor's or postgraduate degree from a PMI GAC-accredited program | 24 |
The experience must fall within the 10 years before you apply and come from a professional setting, though it does not have to be paid. Overlapping projects count once, so count calendar months, not projects. School projects and routine operational work do not qualify.
The 35 hours of project management training must fit the outline, and self-paced courses need an end-of-course assessment. An active CAPM waives the training, but the education and experience rules still apply, and coursework from a GAC-accredited degree can count toward the hours. Books and practice exams alone do not count, and that includes any practice site, this one too.
Check PMI's current training rules before you pay for a live course. The July 2026 outline says training is not limited to one format or provider, and that PMI is adding enhanced verification to the application. Search listings for a PMI blog post, though, describe new limits on which live courses count from December 1, 2026. This page could not confirm those details from PMI directly. Look for it on PMI's site, under the 35-hour training requirement.
PMI can audit any application. You get 90 days to send documents, and your 1-year eligibility period starts once you pass the audit. Failing or refusing it brings a 1-year suspension, so gather your diploma copy, supervisor signatures and training certificates before you apply.
PMP exam format and how to choose where to sit
The 240 minutes work out to 80 seconds a question on average, before any extra reading a case takes. You get two 10 minute breaks, one after the case-study section and one about midway through the independent questions. Once you start a break, you cannot go back to the earlier section, so finish your review first. For online candidates, the outline adds only that the proctor may check your ID after a break, so confirm online break rules with PMI.
PMI lists eight question types:
- Marked for all delivery modes: case or scenario, graphic-based, multiple-choice single response, multiple response.
- Marked for computer-based testing only: enhanced matching, point and click, matching, pull-down list.
You can sit at a Pearson VUE test center or online with a proctor through OnVUE. PMI lists online testing separately from computer-based testing, so the outline reads as if online candidates would not see the second group. It does not spell that out, so confirm before you let it affect your choice. Candidates in Japan and South Korea who test online in their local language are proctored by ATA test services.
Online testing needs a system check and a long check-in, and you must pass an identity verification before you can schedule. If you fail that verification, you are directed to a test center, and a refund request then carries a $100 administrative fee. In Mainland China only paper testing is offered. The online option is closed to People's Republic of China, Macau and Hong Kong citizens wherever they live.
PMI's handbook marks the PMP in English and 15 other languages: Arabic, Bahasa Indonesian, Brazilian Portuguese, French, German, Hebrew, Italian, Japanese, Korean, Polish, Russian, Spanish, Turkish, and both Simplified and Traditional Chinese. On a translated computer exam, a button on each question shows the English text.
Computer exams have a built-in calculator, and you can ask for a handheld one. PMI charges nothing for accommodations, but request them when you pay, because PMI cannot add them to an existing appointment. They may also rule out online testing.
What the PMP exam covers
PMI sets the share of items for each domain. The "About" column is our arithmetic on 170 scored questions, and exact counts can differ by exam form.
| Domain | Weight | About | Tasks |
|---|---|---|---|
| People | 33% | 56 | Common vision, conflicts, leading the team, engaging stakeholders, aligning and managing expectations, knowledge transfer, communication |
| Process | 41% | 70 | Integrated plan, scope, value-based delivery, resources, procurement, finance, quality, schedule, project status, closure |
| Business Environment | 26% | 44 | Governance, compliance, change control, impediments and issues, risk, continuous improvement, organizational change, external changes |
Two changes matter if you are working from old notes. The first is that topics moved. Comparing the January 2021 and July 2026 outlines by topic, risk, change control, issues and governance now sit under Business Environment, while communication and knowledge transfer sit under People. That mapping is ours, because we did not find a PMI crosswalk.
The second is the approach mix. PMI says about 40 percent of items are predictive and the other 60 percent split between adaptive/agile and hybrid, spread through all three domains. If your work is mostly predictive, study agile across the whole outline, not as a separate unit. PMI also treats AI and sustainability as trends behind this outline, and sustainability appears in its compliance and risk tasks.
How long to study for the PMP exam and how to split the time
Start with the weights, then adjust. PMI's documents give no total hours, so this table works per 100 hours. The split is simple arithmetic and our own suggestion, not PMI advice.
| Domain | Hours per 100 | Tasks | Hours per task |
|---|---|---|---|
| People | 33 | 8 | About 4 |
| Process | 41 | 10 | About 4 |
| Business Environment | 26 | 8 | About 3 |
Then work through these steps:
- Read the 26 tasks in PMI's outline and mark any you have not done at work.
- Take a timed practice set in each domain, and move hours toward the weakest tasks. Keep every task above zero, because PMI says each exam addresses all tasks in a domain.
- Practice choosing an action from a scenario. PMI says the exam tests critical thinking on the job and is not written to any single text, so memorized terms will only take you part of the way.
- Before the exam, sit at least one long timed session at 80 seconds a question, with no going back after a break.
How much does the PMP cost, and what can add to it?
We cannot confirm the exam fee, because PMI's PDFs print no amount. The handbook says prices vary by membership status and region, and you must be a member before you pay to get a member rate. These rules are printed:
- Rescheduling or canceling within 30 days of your appointment costs US$70 plus taxes.
- Within 48 hours you cannot reschedule or cancel, and you lose the entire fee if you miss the exam.
- In an emergency such as a medical one, PMI reviews requests case by case, but work reasons do not count. Report a missed exam within 72 hours.
- You can ask for a refund within 30 days of purchase if you have not scheduled and taken the exam in that time. A refund closes your application.
- Fees apply again for a second and third attempt.
- If your 1-year eligibility ends with no exam scheduled, you lose the entire fee and must reapply and pay again.
- If you arrive late, or the name on your ID does not exactly match your scheduling notice, you cannot test. A name mismatch means reapplying and paying again, so check in 30 minutes early and ask PMI about any name change as soon as you can.
- Renewal takes 60 professional development units every 3 years plus a fee. PMI's renewal handbook points to your account for the price.
Candidates in Mainland China follow separate rules for changes and cancellations.
PMP passing score, results and retakes
PMI says the passing score comes from psychometric analysis of what a qualified project manager should be able to do, and its handbook prints no number. After a computer exam you get a report with an overall pass or fail and diagnostic information for each domain. The on-screen result stays preliminary until PMI confirms it. The report is online within 10 business days, and paper results take 6 to 8 weeks.
You have 1 year after approval and up to three attempts. After three failures, you wait 1 year from the last exam before you reapply. If the year simply runs out, you can reapply with no wait.
Free PMP practice test: what to do next
Try the 20 free PMP practice questions on this page: 7 People, 8 Process and 5 Business Environment, with an explanation for every answer. They are newly written practice questions, not real exam questions. All of them are single-response multiple choice, so they do not cover the other seven question types.
VirtuePrep has 810 PMP questions if you want more practice. If you do not yet have the experience, look at CAPM or browse all exams.
20 free PMP practice questions
Answer each one yourself, then open the answer. No account needed. These are study questions, not real exam questions.
-
A logistics company is replacing its route planning system. Three months in, the operations director describes the project to her teams as a way to cut driver hours, while the customer service director tells his team it exists to give customers tighter delivery windows. Backlog discussions are now stalling because each group argues from its own version of the goal. What should the project manager do first?
- Ask the sponsor to rule on which director's goal takes priority and announce the decision to both teams.
- Order the backlog by the operations goal for now, since driver hours are easier to measure than delivery windows.
- Bring the directors and sponsor together to find where their views diverged and agree on one outcome.
- Open a change request that records customer delivery windows as a separate objective in the project charter.
Show answer
Answer: C. The team is working from two versions of the vision, so the first job is to find out why they differ and get the key stakeholders to agree on one shared statement. A ruling or a change request may follow, but neither one tells you what caused the misunderstanding.
Source: PMI, PMP Examination Content Outline, July 2026, People task 1 (p. 7)
-
During an iteration, a tester tells the project manager that a developer keeps merging code without the peer review that both of them accepted in the team's working agreement. The tester has not spoken to the developer about it and asks the project manager to issue a warning. What should the project manager do first?
- Encourage the tester to raise it with the developer directly, and offer to support that conversation.
- Send the developer a written warning so that the breach of the working agreement is on record for later.
- Report the pattern to the developer's functional manager and ask for it to go through performance review.
- Remind the whole team about the peer review rule at the next daily standup without naming anyone.
Show answer
Answer: A. PMI's code of ethics says that the ideal way to handle a disagreement is to go directly to the person involved. The working agreement gives both people a shared basis for that conversation, and the project manager can step in further if it does not settle the matter.
Source: PMI Code of Ethics and Professional Conduct, standard 3.2.7 (p. 8)
-
A team of experienced engineers moved to Scrum a month ago. Each morning they wait for the project manager, now acting as their Scrum Master, to tell each person which items to pick up, and they say this is faster than deciding themselves. Sprint Goals are being met so far. What is the best way for the project manager to respond?
- Keep assigning work while Sprint Goals are being met, and revisit the question after the next release.
- Ask the Product Owner to allocate items to individuals at Sprint Planning so that the morning step is no longer needed.
- Stop attending the Daily Scrum from tomorrow so that the team has to organize itself.
- Coach the team to plan its own daily work, stepping back gradually as its confidence grows.
Show answer
Answer: D. In Scrum, a team decides internally who does what, when and how, and the Scrum Master coaches it toward that. Experienced people who are new to the framework need coaching in the habit, and a sudden withdrawal would give them no help in building it.
-
On a plant upgrade following a predictive plan, the site's environmental compliance manager has skipped every status meeting and does not open the monthly report. At design review she rejects a layout the team spent six weeks on, citing permit conditions that nobody had asked her about. What should the project manager do next?
- Send her each monthly report with a read receipt and copy her manager so that her lack of response is visible.
- Meet her to understand the permit conditions and her needs, then adjust how she is engaged and consulted.
- Escalate the rejection to the sponsor and ask for the layout to be approved so that work can continue.
- Add her to the design review invitation list and ask her to send any objections earlier next time.
Show answer
Answer: B. She holds real influence over the design, and the current meetings and reports are not reaching her. The fix is to understand the permit conditions and her needs, then tailor how she is engaged. PMI's outline lists analyzing stakeholders and tailoring communication under this task.
Source: PMI, PMP Examination Content Outline, July 2026, People task 4 (p. 7)
-
An internal claims department is the customer for a workflow tool delivered in monthly releases. Every release has passed its acceptance criteria and arrived on schedule, yet satisfaction survey scores from claims handlers have fallen for three releases in a row. What should the project manager do next?
- Share the acceptance test results with the department to show that each release met what was agreed.
- Pause releases until the department completes a full requirements review and signs a revised specification.
- Review the feedback with the handlers and product owner to find the gap, then act on it in upcoming work.
- Ask the department head to tell handlers that the tool will improve once all the planned releases are complete.
Show answer
Answer: C. Meeting acceptance criteria does not prove that an internal customer's expectations are being met. This task includes monitoring customer satisfaction and responding, so the next step is to learn what lies behind the falling scores and act on it in the work still to come.
Source: PMI, PMP Examination Content Outline, July 2026, People task 6 (p. 7)
-
A software rollout depends on an integration specialist, the only person who understands a supplier's undocumented interface. She has just given six weeks' notice, and her replacement starts in two weeks. What should the project manager do first?
- Ask her to write everything down during her final week and store the document in the project repository.
- Identify what only she knows that the project depends on, and pair her with the replacement during the overlap.
- Capture her knowledge in the final lessons learned session that is planned for project closure.
- Ask her manager to negotiate a longer notice period so that the handover can wait until integration is finished.
Show answer
Answer: B. The four weeks of overlap are the best chance to pass on this knowledge, so start by working out what is critical, then arrange how it will transfer. Paired work on the real interface can pass on practical know-how that a late document may miss.
Source: PMI, PMP Examination Content Outline, July 2026, People task 7 (p. 8)
-
A hybrid project's steering committee meets tomorrow. Data from the last two iterations shows that a regulatory reporting feature will miss its committed date by about three weeks. The sponsor asks the project manager to leave this out of the report because the team may recover the time. What should the project manager do?
- Leave it out this month and add a full explanation to next month's report if the team has not recovered.
- Report the feature as on track but add a general note that some delivery risks are being watched.
- Send a private note to the committee chair about the slip, and keep the formal report as the sponsor asked.
- Explain to the sponsor why the forecast must be shown, then report it with a recovery option.
Show answer
Answer: D. PMI's code of ethics rules out half-truths and withholding information that would make a statement misleading. The committee needs an accurate view to govern the project, and speaking to the sponsor first keeps that relationship open while the report stays truthful.
Source: PMI Code of Ethics and Professional Conduct, standard 5.3.1 (p. 12)
-
A distribution company will install a conveyor system that needs building permits and equipment with long lead times. The same project includes an operator dashboard, and the operators say they cannot describe what they need until they see early versions. Which delivery approach should the project manager recommend?
- Plan the conveyor work predictively, and build the dashboard in short iterations with operator feedback.
- Plan both predictively, and handle dashboard changes through change requests once requirements are baselined.
- Run both in sprints from a single backlog so that the whole project shares one delivery rhythm.
- Delay the dashboard until the conveyor is running, then define its requirements and plan it predictively.
Show answer
Answer: A. The two parts have different needs. Permits and long lead items reward firm upfront planning, while requirements that emerge from seeing early versions suit iteration, so a hybrid approach fits. PMI's outline expects the project manager to recommend an approach from the project's needs and complexity.
Source: PMI, PMP Examination Content Outline, July 2026, Process task 1 (p. 9)
-
At Sprint Planning, the Product Owner brings an item called 'customer self-service returns' and asks for it to be completed this Sprint. The Developers say it involves label printing, refunds and carrier tracking and cannot be finished within one Sprint. What is the best course of action?
- Start the item now and carry the unfinished part into the next Sprint.
- Extend this Sprint by one week so that the whole item can be finished and reviewed.
- Refine it into smaller items that can each be finished in a Sprint, ordered by the Product Owner.
- Ask for two more Developers for this Sprint so that the team has enough capacity to absorb the full item.
Show answer
Answer: C. Refinement breaks large items into smaller, more precise ones, and an item is ready for selection when the team can finish it within one Sprint. The Product Owner stays accountable for the order, which lets the most valuable piece go first.
-
A retailer funded a self-checkout app to reduce staffed checkout hours. After four releases, the team reports rising velocity and strong feature adoption, but nobody can say whether staffed hours have changed. The product owner wants to start the next release. What should the project manager do next?
- Present the velocity trend and adoption figures to the sponsor as evidence that value is being delivered.
- Add the hours analysis to the closure report, when the full set of features will be in use.
- Proceed with the next release because adoption is strong, and check staffed hours when time allows.
- Agree on a measure, baseline and owner for staffed hours, and use the results to set priorities.
Show answer
Answer: D. Velocity shows how much the team delivers, and adoption shows use, but neither shows the benefit that justified the funding. PMI's outline asks the project manager to verify that benefits are being measured and to examine business value throughout the project, so this should not wait for closure.
Source: PMI, PMP Examination Content Outline, July 2026, Process task 3 (p. 9)
-
A buyer needs a seller to develop and test a new battery module. Technical uncertainty is too high for a credible fixed price, but both parties believe they can negotiate a target cost. The buyer wants the seller to have a direct financial reason to keep costs down. Which contract type fits best?
- Firm fixed price
- Cost plus incentive fee
- Cost plus fixed fee
- Time and materials
Show answer
Answer: B. A cost plus incentive fee contract pays allowable costs and adjusts the fee by a formula comparing actual cost with target cost, so the seller earns more by spending less. It suits development and test work where cost reimbursement is needed and a target can be negotiated. The definitions here come from US federal rules.
Source: Federal Acquisition Regulation, Part 16, sections 16.202, 16.306, 16.405-1 and 16.601
-
A predictive project has a budget at completion of $800,000. At the latest status date, planned value is $350,000, earned value is $300,000 and actual cost is $375,000. The sponsor asks for a forecast of the final cost if the current cost efficiency continues on the remaining work. Which figure should the project manager give?
- $875,000
- $933,000
- $1,000,000
- $1,104,000
Show answer
Answer: C. Cost performance index is earned value divided by actual cost: 300,000 / 375,000 = 0.80. The remaining work is 800,000 minus 300,000, or 500,000, and at 0.80 efficiency it costs 625,000. Adding the 375,000 already spent gives 1,000,000.
-
Two days before a Sprint ends, a story works in the test environment, but the security scan required by the organization's Definition of Done cannot finish until after the Sprint Review. Stakeholders are keen to see the story, and the Product Owner wants to report it as done. What should the team do?
- Leave it out of the completed work, return it to the Product Backlog, and tell stakeholders its status.
- Report the story as done and run the scan in the next Sprint as a follow-up item.
- Ask the Product Owner to waive the scan for this one story and record that waiver in the Sprint Backlog.
- Extend the Sprint by the two days the scan needs so that the review can include the story.
Show answer
Answer: A. Work that does not meet the Definition of Done is not an Increment, cannot be presented at the Sprint Review, and goes back to the Product Backlog for future consideration. An organizational standard sets the minimum for the team, so it is not something to waive for one story, and quality should not be lowered during a Sprint.
Source: The Scrum Guide, 2020, Increment and Definition of Done
-
A predictive schedule has two paths to the finish. Path one is activities A, B and D, lasting 4, 6 and 3 days. Path two is activities A, C and D, with C lasting 2 days. C is now expected to take 8 days because of a late delivery. What is the effect on the project finish?
- No effect, because C was not on the critical path.
- The finish moves 2 days later, and the path through C becomes critical.
- The finish moves 4 days later, and both paths become critical.
- The finish moves 6 days later, and the path through B remains the critical path.
Show answer
Answer: B. Path one takes 13 days and path two originally took 9, so C had 4 days of total float. A 6 day slip uses that float and pushes the finish 2 days, to 15. Path two is now the longest path, which makes it the critical path.
Source: GAO Schedule Assessment Guide, GAO-16-89G, Best Practices 6 and 7
-
A support engineering team uses Kanban with a WIP limit of 10. Over the past month WIP has climbed to 22 as managers asked for more items to be started, throughput has stayed at about 8 items a week, and average cycle time has doubled. A manager says starting more work shows the team is responsive. What should the project manager recommend?
- Raise the WIP limit to 22 so that the board reflects how the team is working now.
- Report WIP as the team's main progress measure, since it shows how much work is currently under way.
- Run a root-cause analysis of the longer cycle times next month while new items keep starting.
- Stop starting new items until WIP returns to the limit, then pull work only as capacity opens.
Show answer
Answer: D. The metrics show more work started but no more finished, with each item taking longer. The Kanban Guide has teams control WIP and start new work only when there is clear capacity. The data already points to the cause, so returning to that pull system comes before any further study.
Source: The Kanban Guide, May 2025, Controlling WIP and flow metrics
-
A project manager is helping set up the governance for a vendor selection panel. Before evaluations start, she learns that her sister is a director at one of the bidding companies. She is confident that she can score the bids fairly. What should she do?
- Disclose the relationship and stay out of the decision unless a mitigation plan is approved and stakeholders consent.
- Stay on the panel and score fairly, then mention the relationship to the sponsor if that company wins the contract.
- Ask her sister's company to withdraw its bid so that the panel's process cannot be questioned later.
- Step off the panel quietly without giving anyone a reason so that the relationship does not affect the process or its result.
Show answer
Answer: A. PMI's code of ethics requires full disclosure of a real or potential conflict of interest to the appropriate stakeholders. She then stays out of the decision unless a mitigation plan is approved and they consent. Her own confidence does not change this, since the code treats the appearance of a conflict as a conflict.
Source: PMI Code of Ethics and Professional Conduct, standards 4.3.1 and 4.3.2 (p. 10)
-
A consumer goods project must use packaging with verified recycled content to meet a regulation in its destination market. Six weeks before launch, a routine check finds that the supplier's certification for the latest batches has lapsed. The packaging itself looks unchanged. What should the project manager do next?
- Accept the batches because the material looks unchanged, and ask the supplier to renew the certification after launch.
- Cancel the supplier's contract and start a new sourcing process so that the launch uses certified material.
- Hold acceptance of the batches, assess the consequences with the compliance owner, and agree on the action.
- Commission a certification audit of all project suppliers and report the findings at the next monthly review.
Show answer
Answer: C. The batches cannot be shown to meet the requirement, so holding them prevents the gap from growing while the facts come in. PMI's outline lists analyzing the consequences of noncompliance and deciding the action needed. Canceling the contract would come before anyone knows whether the lapse can be fixed quickly.
Source: PMI, PMP Examination Content Outline, July 2026, Business Environment task 2 (p. 11)
-
During installation on a predictive project, a client engineer asks the site lead to fit a different sensor model at no extra charge. The site lead agrees verbally and fits it on 3 of 20 units. The sensor is not in the approved baseline. The project manager finds out at the weekly review. What should the project manager do first?
- Update the design documents to show the new sensor, since the client asked for it and no charge applies.
- Pause further installation of that sensor and put the change through change control with an impact assessment.
- Have the three units restored to the baseline sensor at once and tell the client that the request is refused.
- Finish the remaining units with the new sensor so that the system is consistent, then file the change paperwork.
Show answer
Answer: B. A change to an approved baseline needs a formal proposal, an assessment and a decision from whoever holds change authority, even when the client asks for it and pays nothing extra. Pausing limits the problem to the three units already fitted, and the decision may be to keep or reverse them.
Source: NASA Systems Engineering Handbook, section 6.5, Configuration Management
-
On a hybrid customer service project, a team proposes using a third-party generative AI service to draft summaries of support tickets, which contain customer personal data. Nobody in the organization has used this service before. The first trial is planned for the next iteration. What should the project manager do next?
- Allow the trial with a small batch of real tickets, and record any problems in the issue log.
- Reject the proposal, since third-party AI services bring risks that the project cannot control.
- Let the developers decide during the iteration, since self-managing teams choose how they do their own work.
- Log it as a risk, analyze it with security and privacy staff, and define human review before the trial.
Show answer
Answer: D. This is a risk that can be analyzed before anything happens, so it belongs in the risk process and not the issue log. NIST's AI framework calls for mapping risks from third-party data and software and for defined, documented human oversight. A blanket rejection would come before the analysis.
Source: NIST AI Risk Management Framework 1.0, NIST AI 100-1, GOVERN 6, MAP 3.5 and MAP 4
-
An agile payments team is midway through a Sprint when a new national rule is published requiring customer data to be stored in-country within nine months. The release planned for three months from now stores that data abroad. The current Sprint Goal is still valid. What should the project manager do?
- Assess the rule's impact with the Product Owner and compliance staff, then re-order the Product Backlog.
- Ask for the current Sprint to be canceled and replan the whole product around the new rule's requirements.
- Commission a separate legal study of the rule, and make no backlog changes until it is complete.
- Ask the Developers to add the storage work to this Sprint so that the rule is dealt with right away.
Show answer
Answer: A. PMI's outline asks the project manager to assess an external change and prioritize its impact on scope or backlog. Because the Sprint Goal remains valid, the current Sprint can continue, and the Product Owner orders the new work in the backlog based on that assessment.
Source: PMI, PMP Examination Content Outline, July 2026, Business Environment task 8 (p. 12)
What you get with VirtuePrep PMP prep
- 810 practice questions built around the topics the PMP tests.
- An explanation for every answer, so each mistake teaches you something.
- Stats and history that show your weakest topics first.
- Web, iPhone and Android, so you can study wherever you have ten minutes.
PMP practice test questions people ask
What is the PMP passing score?
How long is the PMP exam?
How many questions are on the PMP exam?
What are the PMP certification requirements?
How much does PMP certification cost?
How hard is the PMP exam?
How long should you study for the PMP exam?
What is the PMP pass rate?
PMP vs CAPM: which should you take?
Sources
- PMI: PMP Examination Content Outline, July 2026 (PDF)
- PMI: Certification Handbook, revised June 2026 (PDF)
- PMI: Continuing Certification Requirements Handbook (PDF)
- PMI: PMP Examination Content Outline, January 2021 (PDF), used only for the older figures
VirtuePrep is not affiliated with or endorsed by the organisation that runs the PMP. Exam names are trademarks of their owners. Practice questions are written for study and are not real exam questions. Page updated 2026-11-07.
More Management exams
aPHR (HRCI)
The aPHR exam can feel like a big step, especially if you're just starting out in HR.
ManagementCAPM
The CAPM exam can feel a bit overwhelming when you first start because it throws a lot of project-management terms at...
ManagementCPIM
CPIM is now one exam that covers the topics from the former Part 1 and Part 2.
ManagementPHR (HRCI)
The PHR exam can feel like a lot when you first sit down to study.
Start your PMP prep today
Answer your first question in under a minute. Free to try.