CAPM Practice Test
Practise for the CAPM with 929 exam-style questions, an explanation for every answer and stats that show what to study next.
What is the CAPM exam?
The CAPM exam is the test for PMI's Certified Associate in Project Management: 150 questions in 3 hours, across four domains. You qualify with a secondary degree plus 23 hours of project management education, and PMI's outline lists no project experience requirement. Fundamentals and business analysis together make up 63% of the exam, so most of your study time belongs there.
PMI aims the certification at people interested in or new to project management, and at team members who want to show project knowledge. The version these documents describe began on July 25, 2023. PMI's outline warns that this version differs noticeably from the PMBOK Guide, Seventh Edition, so do not study from that book alone. PMI says each question can be found in at least two books on its reference list, which also includes the Agile Practice Guide and the second edition of Business Analysis for Practitioners.
These facts come from PMI's PDF documents, because its CAPM web page could not be opened when they were checked in November 2026. PMI's 2023 FAQ says it researches the exam content every 5 years, so look at the CAPM page on PMI's site before you book and confirm that the outline, format and reference list still apply. Check the book editions on that list before you buy anything, because a list newer than these documents may name different ones.
CAPM certification requirements
You need both of these:
- A secondary degree, such as a high school diploma, GED or global equivalent.
- 23 hours of project management education, complete by the time you sit the exam.
The hours can come from PMI Authorized Training Partners, PMI chapters, employer programs, training companies, distance-learning companies with an end-of-course assessment, or university programs. Chapter meetings do not count, unless at least 1 hour is a learning activity, and then only those hours count.
Do not assume that reading a book by yourself counts. PMI's outline mentions self-study guides from those provider types, but its older 2020 handbook excluded self-directed reading and videos. Confirm with PMI before you rely on self-study.
PMI says it processes applications in 24 hours or less, unless yours is selected for audit. Approval starts a 1-year eligibility period. If you are audited, the period starts once you complete the audit.
CAPM exam format
| Item | Official detail |
|---|---|
| Questions | 150: 135 scored and 15 unscored pretest, placed at random |
| Time | 3 hours, plus an optional tutorial and survey (5 to 15 minutes) outside that time |
| Break | One 10-minute break after question 75 |
| Item types | Multiple choice, drag and drop, hot spot, animation video, comic strip |
| Delivery | Test center or online proctored; paper only in Mainland China |
| Result | Pass or fail, with diagnostic information for each domain |
Three details affect how you sit the exam. Once you start the break, you cannot go back to questions 1 to 75, so review them first. If you test online, you will see comic strips and no animations, which PMI says avoids sound issues. Online proctoring is not offered to citizens of the People's Republic of China, Macau and Hong Kong, wherever they are.
What the CAPM exam covers
| Domain | Weight | Rough questions out of 150 |
|---|---|---|
| 1. Project Management Fundamentals and Core Concepts | 36% | About 54 |
| 2. Predictive, Plan-Based Methodologies | 17% | 25 to 26 |
| 3. Agile Frameworks/Methodologies | 20% | About 30 |
| 4. Business Analysis Frameworks | 27% | 40 to 41 |
The question counts are our arithmetic from PMI's percentages, because PMI publishes weights and not counts. PMI says it holds to these percentages at the domain level, while the number of each question type and approach can vary by form.
Domain 1 is about telling similar things apart: a project from a program, a risk from an issue, a project manager from a sponsor, leadership from management. It also includes the PMI Code of Ethics. Domain 2 covers when a plan-based approach fits, critical path methods, work breakdown structures, and cost and schedule variance. Domain 3 covers when an adaptive approach fits, planning iterations, and the parts of Scrum, Extreme Programming, SAFe and Kanban.
Domain 4 has six tasks, more than any other domain. They start with stakeholder roles and move through gathering requirements, product roadmaps and acceptance criteria to deciding whether a product is ready to deliver. At 27%, it outweighs predictive or agile taken alone.
PMI also says predictive, adaptive and business analysis approaches appear throughout all four domains. So expect an agile scenario in a question about roles, or a requirements question set inside a predictive project.
How to split your CAPM study time
Start with the weights, then adjust for your own gaps. The PMI documents we checked give no study-hour figure, so the total is yours to set. The split below is our judgment, based on those weights. For a 40-hour plan, it looks like this:
| Domain | Hours | Where the time goes |
|---|---|---|
| 1. Fundamentals | 14 | Paired terms, roles, risk and stakeholder registers, ethics scenarios |
| 2. Predictive | 7 | Critical path and variance practice, work packages, when to choose this approach |
| 3. Agile | 8 | Comparing the four methods, iteration planning, adaptive artifacts |
| 4. Business analysis | 11 | One block for each of the six tasks |
Then adjust it in two ways. Keep Domain 2 hands-on even though it is small, because the outline's calculations sit there and they take practice rather than rereading. Also move hours away from whatever you already do at work. If you run sprints every day, part of the Domain 3 time may do more good in Domain 4.
A simple order for the next few weeks:
- Read PMI's outline and mark every task you could not explain to a colleague.
- Study one domain at a time, starting where you are weakest relative to the domain's weight.
- Practice with mixed questions, because the real exam places them at random.
- Sit a timed run of 150 questions, with a break after question 75 and no return to the first half.
CAPM cost, retakes and renewal
PMI's current handbook gives no price and says fees may vary by membership status and region. A member rate applies only if your membership is in place before you pay. Rescheduling or canceling within 30 days of your appointment costs US$70 plus taxes. Inside 48 hours you cannot reschedule, and if you do not attend you forfeit the entire exam fee. Candidates testing in Mainland China follow the policies on CITEF's website instead.
PMI reviews emergencies that force a late change or a missed appointment case by case. You can ask for a refund within 30 days of purchase, as long as you do not schedule and take the exam in that time. A refund closes your application and ends your eligibility period. To book an online appointment you must first pass an identity check. If you fail it, you are directed to a test center, and a refund request after that failure loses a $100 administrative fee.
You can sit the exam up to three times in your 1-year eligibility period, and retakes carry a fee. After three failed attempts, you wait 1 year from the last one before reapplying for the CAPM, though you can apply for a different PMI certification in that time.
Renewal comes every 3 years and takes 15 PDUs. At least 9 must be education, with at least 2 each in Ways of Working, Power Skills and Business Acumen. Up to 6 can be giving back. Fee amounts depend on membership and region, so check them with PMI.
CAPM practice test: what to do next
Try the 20 free CAPM practice questions on this page. They were newly written for practice, roughly follow the official domain weights and are not real exam questions. For more, VirtuePrep has 929 CAPM questions with an explanation for every answer, and you can browse other exams too.
20 free CAPM practice questions
Answer each one yourself, then open the answer. No account needed. These are study questions, not real exam questions.
-
A hospital renovation's risk register lists the possibility that a supplier could miss the delivery date for electrical switchgear. This morning the supplier confirmed that the date has been missed and the equipment will arrive three weeks late. How should the project coordinator now treat this item?
- As a risk, since it was identified and logged before the supplier missed the date
- As an issue, since it has now happened and needs action from the project's management
- As an assumption, since the original delivery date was an estimate that proved to be false
- As a constraint, since the late delivery now restricts what the installation crew can do
Show answer
Answer: B. A risk is uncertain and still ahead. An issue has already happened and now needs management action. The late delivery began as a logged possibility, but the supplier has now confirmed it, so handle it as an issue.
-
A project coordinator is one of three people scoring vendor proposals. Partway through, she learns that one bidder is owned by her brother-in-law. She is confident she can still score every proposal objectively. According to the PMI Code of Ethics and Professional Conduct, what should she do?
- Keep scoring and attach a written justification to every score she gives each vendor
- Ask the bidder to withdraw from the process so that the conflict no longer exists
- Tell the appropriate stakeholders and stay out of scoring until they agree on a way forward
- Finish her scoring and then mention the relationship once the contract has been awarded
Show answer
Answer: C. The Code's fairness standards require proactive, full disclosure of a real or potential conflict of interest. She must also stay out of the decision until the appropriate stakeholders have the facts, have approved a plan to manage the conflict and have consented to her continuing. Feeling sure of her own objectivity does not change this.
Source: PMI Code of Ethics and Professional Conduct, Fairness: mandatory standards
-
A draft schedule shows "Design approved" as a milestone with a five-day duration and two reviewers assigned, because the reviewers need five days to read the design. What is the best fix?
- Add a five-day task for the reviewers, followed by a zero-duration milestone
- Keep the five days on the milestone and remove the two reviewers from the entry
- Keep the entry as it is and change its label from a milestone to a work package
- Remove the entry from the schedule and record the design approval in the status report
Show answer
Answer: A. A milestone marks a point in time, so it has no duration and uses no resources. The reading takes time and people, so it belongs in a task. The milestone then marks the moment approval is achieved.
Source: GAO Schedule Assessment Guide (GAO-16-89G), milestone, detail and summary activities
-
A project to install a clinic's appointment system has delivered its full scope and is about to close. Two risks remain open, and the expected drop in missed appointments cannot be measured for another year. What should happen to these items at closure?
- Keep the project open until the benefit can be measured and both risks have expired
- Mark both risks as closed and remove the benefit, since the project is now finished
- Leave them with the project manager, who follows up on them after the team has disbanded
- Hand them over to the business owner, who accepts responsibility for tracking them
Show answer
Answer: D. A controlled closure transfers ongoing risks, issues, actions and benefit tracking to the business, which accepts responsibility for them. The temporary project can then end, and the remaining items still have an owner.
Source: UK Government Functional Standard GovS 002: Project delivery, section 6.4.8 on project closure
-
Midway through a software rollout, a new regulation adds work that the approved budget cannot cover. The extra funding is above the project manager's authority. Which split of responsibilities fits best?
- The project manager approves the funding, and the sponsor replans the team's daily work
- The project manager assesses the impact and options, and the sponsor decides on the funding
- The team votes on the funding, and the sponsor records the result in the project plan
- The sponsor rewrites the task assignments, and the project manager updates the business case
Show answer
Answer: B. The project manager runs day-to-day delivery and brings forward what a problem means for the project. A decision above the project manager's authority goes up to the senior role accountable for the business case and objectives. The UK standard cited here calls that role the senior responsible owner, with a sponsoring body above it, while PMI's outline uses the word sponsor.
-
The risk plan for a data migration says that if the lead tester is unavailable for more than two days, a named contractor will be called in. The lead tester has just been told to stay off work for a week on medical advice. What should the project coordinator do?
- Put the agreed contingency plan into action and update the risk register
- Run a new risk analysis to decide whether a contractor is the right choice
- Wait to see whether testing falls behind before contacting the contractor
- Submit a change request to extend the schedule by the length of the absence
Show answer
Answer: A. A contingency plan is prepared in advance for a known risk. The plan's condition has now been met, so carry out the agreed response and keep monitoring the item until it is closed.
-
A team's 15-minute daily standup has run to 40 minutes for three days because two developers debate a database design while everyone else waits. Which change would most improve the meeting?
- Schedule the standup for 45 minutes so that the design debate can be finished
- Suspend the daily standups until the database design question has been settled
- Return the standup to progress toward the goal and hold the design talk separately
- Have the Scrum Master settle each design question during the standup itself
Show answer
Answer: C. A daily standup is a short check of progress toward the goal, plus any adjustment to the plan. Detailed discussions can happen at other times in the day among the people who need them. The standup stays short, and the design question gets the time it needs.
-
A city is building a concrete pedestrian bridge. The design has been permitted, the requirements are set by building codes, and changing the structure after the concrete is poured would be very costly. Which approach best fits this project?
- An adaptive approach, with a new portion of the bridge reviewed by users every two weeks
- A Kanban approach, pulling structural work as crews are free, with no planned end date
- A prototyping approach, with the scope reset after every stakeholder demonstration
- A predictive approach, with design, procurement and construction done in planned order
Show answer
Answer: D. A predictive approach gathers requirements up front and works through planned stages in order, without returning to earlier ones. That suits this bridge: the design is permitted, building codes set the requirements, and poured concrete is very costly to change. The reference names bridges and buildings as work that needs a sequential approach.
Source: GOV.UK Service Manual, Agile delivery: Agile and government services, an introduction
-
A project has two paths from start to finish. Path 1 is A (4 days), B (6 days), E (3 days). Path 2 is A (4 days), C (2 days), D (3 days), E (3 days). Activity C is delayed by 3 days, and nothing else changes. What is the effect on the project?
- The finish moves out 2 days, and the path through C and D becomes the critical path
- The finish moves out 3 days, and the path through B remains the only critical path
- The finish does not move, because C was not on the critical path at the start
- The finish moves out 1 day, and both of the paths become equally critical
Show answer
Answer: A. The critical path is the longest path. Path 1 takes 13 days and Path 2 takes 12, so Path 2 has 1 day of float. A 3-day delay takes Path 2 to 15 days, which makes it the longest path. The project now takes 15 days instead of 13, so the finish moves out 2 days.
Source: GAO Schedule Assessment Guide (GAO-16-89G), critical path and total float
-
At a monthly status review, a project shows planned value of $80,000, earned value of $72,000, and actual cost of $90,000. Which statement correctly describes its performance?
- Cost variance is -$8,000 and schedule variance is -$18,000, so it is over cost and behind plan
- Cost variance is +$18,000 and schedule variance is +$8,000, so it is under cost and ahead of plan
- Cost variance is -$18,000 and schedule variance is -$8,000, so it is over cost and behind plan
- Cost variance is -$10,000 and schedule variance is -$8,000, so it is over cost and behind plan
Show answer
Answer: C. Cost variance is earned value minus actual cost: $72,000 minus $90,000 is -$18,000. Schedule variance is earned value minus planned value: $72,000 minus $80,000 is -$8,000. Negative values mean the work is costing more than budgeted and less work is done than planned.
Source: GAO Cost Estimating and Assessment Guide (GAO-20-195G), earned value management
-
A university is planning a student advising app. Nobody yet knows which features students will use, and leaders want to see students trying it within weeks. Which benefit is the strongest reason to choose an adaptive approach?
- The full scope and the final budget can be locked in before any building starts
- Feedback on working versions can change the plan while the work is under way
- Business leaders need to be involved much less once the team has started work
- Estimates and written requirements stop being needed once a first version is out
Show answer
Answer: B. The needs here are uncertain, so learning early is worth a lot. Adaptive approaches deliver working product frequently and accept changing requirements, even late on. Each version gives the team evidence from real students about what to do next.
-
A team moving to two-week sprints inherits a work breakdown structure containing a work package called "online payment module," estimated at ten weeks. How should this be handled in iteration planning?
- Extend the next sprint to ten weeks so the whole module can be completed at once
- Keep it as one backlog item and carry it from sprint to sprint until it is finished
- Assign design to one sprint, coding to the next few, and testing to the final sprint
- Break it into smaller backlog items that can each be completed within a single sprint
Show answer
Answer: D. An item is ready for selection when the team can bring it to Done within one sprint, and refinement breaks large items into smaller, more precise ones. Each increment must be usable, so each smaller item should be able to meet the Definition of Done.
-
An IT support team using a Kanban board receives requests at unpredictable times. The board now shows 25 items started and very few finished, and members keep switching between them. Which action best applies Kanban to this problem?
- Limit the work in progress and start new items only when capacity becomes available
- Begin every request as soon as it arrives so that no customer is ever left waiting
- Move the team to fixed sprints and hold a review meeting at the end of each one
- Give every request a story point estimate before it is allowed onto the board
Show answer
Answer: A. Kanban controls the number of items between started and finished. Doing so should create a pull system, where new work starts only when there is a clear signal of capacity, and it often improves the team's focus too. The guide's term is controlling WIP, which here means setting a limit on active items.
Source: The Kanban Guide, May 2025
-
A developer says a story's code is complete, but the Definition of Done also requires automated tests and a security scan. Neither has been run, and neither can finish before tomorrow's Sprint Review. The Product Owner would like to show the story. What should happen?
- Show the story at the review and tell stakeholders that the final checks are pending
- Remove the two checks from the Definition of Done for this sprint only
- Leave the story out of the review and return it to the Product Backlog
- Have the Product Owner sign a waiver so that the story can count as complete
Show answer
Answer: C. The Definition of Done sets the shared meaning of complete. Under the Scrum Guide, an item that falls short of it cannot be released or presented at the Sprint Review. It goes back to the Product Backlog to be considered for later work.
-
On a Scrum project, a sales director asks the business analyst to move a customer-requested feature to the top of the Product Backlog before a sales event. How should the business analyst respond?
- Reorder the backlog, since business analysts are responsible for what requirements mean
- Ask the Scrum Master to decide, since this person keeps the Scrum process running
- Ask the Developers to start it next, since they select the work during each sprint
- Take the request to the Product Owner, who is accountable for the backlog's order
Show answer
Answer: D. The Product Owner is accountable for ordering the Product Backlog, and anyone who wants it changed needs to persuade that person. The business analyst can help by setting out the request and its business reasons clearly.
-
A business analyst discovers that two feature teams read the same pricing requirement differently: one assumes prices include tax, and the other assumes they do not. Both teams are building against it this week. What is the best way to communicate here?
- Add a note on the difference to the monthly project status report
- Bring both teams together for a short conversation and record what is decided
- Email the full requirements document to both teams and ask them to reread it
- Ask the project manager to raise the difference at next week's team leads meeting
Show answer
Answer: B. The misunderstanding is urgent and needs back-and-forth between the people doing the work. The Agile principles name face-to-face conversation as the most efficient and effective way to convey information to and within a team. Recording the decision then gives both teams one version of the requirement.
-
A business analyst needs to learn why caseworkers are bypassing a screen in the claims system. Early conversations suggest some are reluctant to discuss this in front of their managers. Which requirements gathering approach fits best?
- One-to-one interviews with individual caseworkers
- A group workshop with caseworkers and their managers
- A lessons learned session with the team that built the screen
- A review of the original signed requirements document
Show answer
Answer: A. Participants in a group may not feel comfortable speaking openly, and mixed seniority makes this harder. When a group adds little, individual methods such as in-depth interviews suit better. One-to-one sessions give each caseworker room to explain what really happens.
Source: GOV.UK Service Manual, User research: Researching in small group workshops
-
Executives and partner teams ask for a simple view of how a product is likely to develop over the next 18 months. Near-term priorities are fairly clear, while later plans are still uncertain. What should the business analyst help prepare?
- A sprint backlog of the tasks that the team expects to do over the 18 months
- A roadmap that commits to specific features and ship dates across the 18 months
- A roadmap that shows stages by time period and describes the later ones as intent
- A requirements traceability matrix that links planned features to test results
Show answer
Answer: C. A roadmap shows how a product is likely to develop over time, in a form that is simple to read and easy to adjust. It is not a backlog, and it captures intent rather than solutions. The further ahead a stage lies, the more uncertain it is, so exact dates and features for all 18 months would promise too much.
Source: GOV.UK Service Manual, Agile delivery: Developing a roadmap
-
A business analyst used to producing a full signed-off requirements document before design begins joins an adaptive team. Which change in how the analyst works fits best?
- Finishing the complete specification before the first iteration, then handing it over
- Writing acceptance criteria only after the team has finished building each item
- Ceasing to record requirements, since developers can now speak directly with users
- Turning needs into user stories with the team, and refining them as the work proceeds
Show answer
Answer: D. An adaptive team expects needs to change as it learns, so a complete specification up front no longer fits. The reference describes the business analyst turning user needs, business needs and constraints into user stories. The stories can then be refined as the work proceeds.
Source: GOV.UK Service Manual, The team: What each role does in a service team
-
Before a planned release, a business analyst reviews the requirements traceability matrix. Of 40 approved requirements, 38 have passed verification, one failed its acceptance test, and one has no test linked to it. What is the best conclusion?
- The product is ready, because 95 percent of the requirements have passed verification
- The product is not ready until those two requirements are resolved or formally changed
- The product is ready, because the requirement with no test has not been shown to fail
- The product is not ready until all 40 requirements have been rewritten and verified again
Show answer
Answer: B. Traceability links each requirement to its verification results, with the goal of verifying all of them. Here one requirement has failed and another has no evidence behind it. Either they are resolved, or a change to those requirements goes through authorized change control.
Source: NASA Systems Engineering Handbook, 6.2 Requirements Management
What you get with VirtuePrep CAPM prep
- 929 practice questions built around the topics the CAPM tests.
- An explanation for every answer, so each mistake teaches you something.
- Stats and history that show your weakest topics first.
- Web, iPhone and Android, so you can study wherever you have ten minutes.
CAPM practice test questions people ask
What are the CAPM certification requirements?
What is the CAPM exam format?
What is the CAPM passing score?
What is the CAPM pass rate?
How much does the CAPM exam cost?
Should you get CAPM before PMP?
Is PMP harder than CAPM?
How hard is the CAPM exam?
Is a CAPM worth it?
Sources
- PMI, CAPM Examination Content Outline, 2023 exam update (file saved September 2025)
- PMI Certification Handbook, revised June 2026
- PMI Continuing Certification Requirements Handbook, April 2026
- PMI, CAPM 2023 Exam Update FAQ, April 2023
- PMI, older CAPM Handbook, January 2020 (for the self-study point only)
VirtuePrep is not affiliated with or endorsed by the organisation that runs the CAPM. Exam names are trademarks of their owners. Practice questions are written for study and are not real exam questions. Page updated 2026-11-07.
More Management exams
aPHR (HRCI)
The aPHR exam can feel like a big step, especially if you're just starting out in HR.
ManagementCPIM
CPIM is now one exam that covers the topics from the former Part 1 and Part 2.
ManagementPHR (HRCI)
The PHR exam can feel like a lot when you first sit down to study.
ManagementPMP
The PMP exam can feel overwhelming at first because it mixes everything, planning, people issues, risk, budgets, change...
Start your CAPM prep today
Answer your first question in under a minute. Free to try.